Utilities:
Skepticism Pays Off
Cautious approach to huge power requests helped insulate electric
industry
March 21, 2002 -- For electric utilities, skepticism about
huge power requests from carrier hotels proved critical to their
mission.
In
2000 and 2001, power companies in major cities were overwhelmed
with requests for huge capacity from telecom hotel projects, according
to Steve Rosenstock, of the Edison Electric Institute (EEI), an
industry group representing power companies.
Most of those utilities insisted that carrier hotel developers
share the financial risk of adding additional capacity, a move
that insulated the power companies when projects tanked and demand
never approached projected levels.
"No
one is seeing 300 watts per square foot," said Rosenstock.
"No one is seeing 200 watts per square foot. When I see it,
I'll believe it and I'll build it for you."
Energy
issues are a hot-button topic whenever telecom developers gather
at industry events. At the IMN Forum on Carrier Hotels and Internet
Data Centers earlier this month in New York, Rosenstock provided
the utilities' perspective.
Initial
requests for additional generation and transmission capacity for
carrier hotels and data centers surprised the utility industry,
Rosenstock said.
At
one point, Chicago's Commonwealth Edison had requests for power
from 31 planned telecom facilities, which projected the need for
an additional 1,164 megawatts of system load. In New York, 46
proposed facilities sought to add 500 megawatts of demand to ConEdison's
system.
Existing electric infrastructure would not have been able
to handle that demand, and adding additional capacity is expensive,
ranging from $400 to $1,000 per kilowatt, according to EEI. Even
at the low end of $400, supplying the 1,164 megawatt request for
Chicago facilities would cost $465 million.
"It's
like turning two-lane roads into superhighways," said Rosenstock.
"Who's going to pay for that?"
Alarmed
by these numbers, EEI began working with its members to track
power usage by carrier hotels. The goal was to craft a
strategy that could meet these customers' unique needs without
incurring speculative upgrade costs that might wind up being borne
by the utilities' other customers and shareholders.
Utilities
soon began requiring security deposits from carrier hotel developers
to offset the cost of upgrading systems to meet capacity requests.
ComEd, PSE&G and Florida Power & Light are among the power
companies requiring these deposits, which are generally refunded
once loads reach certain milestones.
Not surprisingly,
the data thus far shows demand has amounted to a fraction of requested
capacity.
In
California, PG&E has seen an increase of 50 megawatts, well
short of the 341 megawatts requested by telecom developers, according
to EEI's numbers. In Austin, Texas, a projected 100 megawatts
of additional demand dwindled to just 5 megawatts of actual use.
Rhetoric
about the high financial cost of facility downtime is often laden
with hype, according to Rosenstock, who noted that some service
providers asserted that data center downtime would cost them $1
million an hour.
"A
million dollars an hour equates to $8.76 billion a year,"
noted Rosenstock, who was skeptical that any providers were bringing
in that kind of revenue.
|